In the competitive commercial software market, software companies feel
compelled to release software the moment it is ready. Their task is treacherous, treading
the line between releasing poor quality software early and high quality software late. A
good answer to the question, "Is the software good enough to release now?" can
be critical to a companys survival. The answer is sometimes based on gut instinct,
but several techniques can put this judgment on a firmer footing.
Defect Density
One of the easiest ways to judge whether a program is ready to release
is to measure its defect densitythe number of defects per line of code. Suppose that
the first version of your product, GigaTron 1.0, consisted of 100,000 lines of code, that
you detected 650 defects prior to the softwares release, and that 50 more defects
were reported after the software was released. The software therefore had a lifetime
defect count of 700 defects, and a defect density of 7 defects per thousand lines of code
(KLOC).
Suppose that GigaTron 2.0 consisted of 50,000 additional lines of code,
that you detected 400 defects prior to release, and another 75 after release. The total
defect density of that release would be 475 total defects divided by 50,000 new lines of
code, or 9.5 defects per KLOC.
Now suppose that youre trying to decide whether GigaTron 3.0 is
reliable enough to ship. It consists of 100,000 new lines of code, and youve
detected 600 defects so far, or 6 defects per KLOC. Unless you have a good reason to think
that your development process has improved with this project, your experience should lead
you to expect between 7 and 10 defects per KLOC. The number of defects you should attempt
to find will vary depending on the level of quality youre aiming for. If you want to
remove 95 percent of all defects before shipping, you would need to detect somewhere
between 650 and 950 pre-release defects. This technique suggests that the product is not
quite ready to ship.
The more historical project data you have, the more confident you can be
in your pre-release defect density targets. If you have data from only two projects and
the range is as broad as 7 to 10 defects per KLOC, that leaves a lot of wiggle room for an
expert judgment about whether the third project will be more like the first or second. But
if youve tracked defect data for 10 projects and found that their average lifetime
defect rate is 7.4 defects per KLOC with a standard deviation of 0.4 defects, you have a
great deal of guidance indeed.
Defect Pooling
Another simple defect prediction technique is to separate defect reports
into two pools. Call them Pool A and Pool B. You then track the defects in these two pools
separately. The distinction between the two pools is arbitrary. You could put all the
defects discovered on Mondays, Wednesdays, and weekends into Pool A, and the rest of the
defects into Pool B. Or you could split your test team down the middle and put half of
their reported defects into one pool, half into the other. It doesnt really matter
how you make the division as long as both reporting pools operate independently and both
test the full scope of the product.
Once you create a distinction between the two pools, you track the
number of defects reported in Pool A, the number in Pool B, andheres the
important partthe number of defects that are reported in both Pool A and Pool
B. The number of unique defects reported at any given time is:
DefectsUnique =
DefectsA + DefectsB - DefectsA&B
The number of total defects can then be approximated by the simple
formula:
DefectsTotal = (
DefectsA * DefectsB ) / DefectsA&B
If the GigaTron 3.0 project has 400 defects in Pool A, 350 defects in
Pool B, and 150 of the defects in both pools, the number of unique defects detected would
be 400 + 350 - 150 = 600. The approximate number of total defects would be 400 * 350 / 150
= 933. This technique suggests that there are approximately 333 defects yet to be detected
(about a third of the estimated total defects); quality assurance on this project still
has a long way to go.
Defect Seeding
Defect seeding is a practice in which defects are intentionally inserted
into a program by one group for detection by another group. The ratio of the number of
seeded defects detected to the total number of defects seeded provides a rough idea of the
total number of unseeded defects that have been detected.
Suppose on GigaTron 3.0 that you intentionally seeded the program with
50 errors. For best effect, the seeded errors should cover the full breadth of the
products functionality and the full range of severitiesranging from crashing
errors to cosmetic errors.
Suppose that at a point in the project when you believe testing to be
almost complete you look at the seeded defect report. You find that 31 seeded defects and
600 indigenous defects have been reported. You can estimate the total number of defects
with the formula:
IndigenousDefectsTotal = ( SeededDefectsPlanted /
SeededDefectsFound ) * IndigenousDefectsFound
This technique suggests that GigaTron 3.0 has approximately 50 / 31 *
600 = 967 total defects.
To use defect seeding, you must seed the defects prior to the beginning
of the tests whose effectiveness you want to ascertain. If your testing uses manual
methods and has no systematic way of covering the same testing ground twice, you should
seed defects before that testing begins. If your testing uses fully automated regression
tests, you can seed defects virtually any time to ascertain the effectiveness of the
automated tests.
A common problem with defect seeding programs is forgetting to remove
the seeded defects. Another common problem is that removing the seeded defects introduces
new errors. To prevent these problems, be sure to remove all seeded defects prior to final
system testing and product release. A useful implementation standard for seeded errors is
to require them to be implemented only by adding one or two lines of code that create
the error; this standard assures that you can remove the seeded errors safely by
simply removing the erroneous lines of code.
Defect Modeling
A colleague of mine recently added several hundred lines of code to an
existing program in one sitting. The first time he compiled the code, he got a clean
compile with no errors. His initial coding appeared to be flawless. When he tried to test
the new functionality, however, he found that it didnt exist. When he reexamined his
new code, he found that his work had been embedded between a preprocessor macro that
deactivated the new code. When he moved the new code outside the scope of the macro, it
produced the usual number of compiler errors.
With software defects, no news is usually bad news. If the project has
reached a late stage with few defects reported, there is a natural tendency to think,
"We finally got it right and created a program with almost no defects!" In
reality, no news is more often the result of insufficient testing than of superlative
development practices.
Some of the more sophisticated software project estimation and control
tools contain defect modeling functionality that can predict the number of defects you
should expect to find at each point in a project. By comparing defects actually detected
to the number predicted, you can assess whether your project is keeping up with defect
detection or lagging behind.
Combinations
Evaluating the combinations of defect density, defect pools, and defect
seeding will give you more confidence than you could have in any of techniques
individually. Examining defect density alone on GigaTron 3.0 suggested that you should
expect 700 to 1000 total lifetime defects, and that you should remove 650 to 950 before
product release to achieve 95 percent pre-release defect removal. If you had detected 600
defects, the defect density information alone might lead you to declare the product
"almost ready to ship." But defect pooling analysis estimates that GigaTron 3.0
will produce approximately 933 total defects. Comparing the results of those two
techniques suggests that you should expect a total defect count toward the high end of the
defect density range instead of the low end. Because the defect seeding technique also
estimates a total number of defects in the 900s, GigaTron 3.0 appears to be a relatively
buggy program.
Resources
The popular literature doesnt have much to say about defect
prediction. A notable exception is Glenford Myers 1976 book, Software Reliability
(Wiley). Lawrence H. Putnam and Ware Myers discuss the specific topic of defect modeling
at some length in Measures for Excellence (Yourdon Press 1992).
Editor: Steve McConnell, Construx Software, 11820 Northup
Way
#E200, Bellevue, WA 98005.
E-mail: steve.mcconnell@construx.com - WWW: http://www.construx.com/stevemcc/