“Hope is a good
breakfast, but it is a bad supper.”
—Francis Bacon
Software problems have persisted partly
because of the bewitching appeal of a few common, ineffective
practices. During the California gold rush in the
late 1840s and early 50s, some prospectors were deceived by
fool’s gold—iron pyrite—a substance that has the luster and
sparkle of gold. Unlike gold, iron pyrite is flaky, brittle, and
virtually valueless. Experienced miners know that real gold is
soft, malleable, and doesn’t break under pressure. For 50 years,
software developers have been succumbing to the temptation of
their own fool’s gold. They are drawn to flawed practices that
have a seductive appeal, but the practices that make up
software’s fool’s gold, like iron pyrite, are flaky, brittle,
and virtually valueless.
Moving the Block
Looking back many centuries before the
California gold rush, suppose that you were working on one of
the ancient pyramids and were given the assignment to move an
enormous stone block 10,000 meters from a river to the site of a
pyramid under construction, as shown in Figure 2-1. You are
given 100 days to move the block and 20 people with which to
move it.
Figure 2-1
One way to think of a software project is
as a heavy block of stone. You must either move the block one
day closer to the final destination each day, or you must do
something that will enable you to traverse the remaining
distance in one less day.
You are allowed to use any method you like
to get it to its destination. Each day, you have to move the
block an average of 100 meters closer to the pyramid, or you
have to do something that will reduce the number of days needed
to travel the remaining distance.
Some block-moving teams might immediately
begin pushing the block, trying to move it with brute force.
With a very small block, this method might work, but with a
heavy block resting directly on desert sand, this approach won’t
move the block very quickly, if at all. If the block moves 10
meters per day, the fact that it is moving at all might be
satisfying, but the team is actually falling 90 meters per day
behind. “Progress” doesn’t necessarily mean sufficient progress.
The smart block-moving team wouldn’t jump
straight into trying to move the block with brute force. They
know that for all but the smallest blocks, they will need to
spend time planning how to move the block before they put their
muscles into it. After analyzing their assignment, they might
decide to cut down a few trees and use the tree trunks as
rollers, as shown in Figure 2-2. That will take a day or two,
but chances are good that it will increase the speed at which
they can move the block.
What if trees aren’t readily available, and
the team has to spend several days hiking up river to find any
trees? The hike is still probably a good investment, especially
since the team that begins by trying to use brute force will
only move the block a fraction of the distance needed each day.
Similarly, the smart block-moving team
might want to prepare the surface over which they’ll be moving
the block. Instead of pushing it across the sand, they might
want to create a level roadway first, which will be an
especially good idea if they have more than just this one block
to move.
Figure 2-2
Whether moving a block of stone or
creating computer software, the smart team takes time at the
beginning of the project to plan its work so that it can work
quickly and efficiently.
A really sophisticated block-moving team
might start with the roller and road system, and eventually
realize that having only the minimum number of rollers available
forces them to stop work too often; they have to move the back
roller to the front of the block every time they move the block
forward one roller-width. By having a few extra rollers on hand
and assigning some people to move the rollers from back to
front, they’re better able to maintain their momentum.
They might also realize that their pushing
is limited by how many people can fit around the block’s base.
They might create a harness so that they can pull the block from
the front at the same time they’re pushing it from behind, as
illustrated in Figure 2-3. As more people divide the work, they
find that each person’s work is easier, and the faster pace is
actually more sustainable than the slower one.
Figure 2-3
Smart teams continuously look for ways to
work more efficiently.
Stone Blocks and Software
How does this block moving relate to
software? The movement of the stone block is analogous to
creating source code. If you have 100 days to complete a
software project, you either need to complete 1/100
of the source code each day, or you need to do work that will
allow you to complete the remaining source code faster. Because
the work of creating source code is much less tangible than the
work of moving a stone block, progress at the beginning of a
software project can be harder to gauge. Software projects are
vulnerable to a “last minute syndrome” in which the project team
has little sense of urgency at the beginning of a project,
fritters away days on end, and works itself into a desperate
frenzy by the end of the project. Thinking of a project’s source
code as a stone block makes it clear that you can’t hope to
conduct a successful project by sprinting at the end. Every day,
a software project manager should ask, “Did we move the block
one day closer to our destination today? If not, did we reduce
our remaining work by one day?”
Another way that moving a stone block
relates to software is that, eventually, no matter how much
planning you do, you do have to move the block; you do have to
write the source code. Source-code creation on all but the
smallest projects involves an enormous amount of detail work,
and it’s easy to underestimate it.
Code-and-Fix Development
The problem of not focusing enough on
making rollers and preparing roadways is by far the most common
problem in software. About 75 percent of the software project
teams begin their projects by hurling themselves against the
block and trying to move it with brute force.[1]
This approach is called “code-and-fix development”—jumping
straight into coding without planning or designing the software
first. Sometimes teams do this because the team’s software
developers are anxious to begin coding. Sometimes they do it
because managers or customers are eager to see tangible signs of
progress. Code-and-fix development is universally ineffective on
all but the tiniest projects.
The problem with the code-and-fix approach,
as with the brute force approach to moving the stone block, is
that quick movement off the starting line doesn’t necessarily
translate into quick progress toward the finish line. The team
that uses a more advanced approach is putting a framework in
place that will allow the project to spin up to a high level of
productivity and finish efficiently. It is putting rollers under
the block, clearing the roadway, and preparing to focus the
energy of the project team. The code-and-fix project gets the
block moving early, but it doesn’t move the block far enough
each day and the brute force approach isn’t sustainable. It
typically leads to the creation of hundreds or thousands of
defects early in the project. Several studies have found that 40
to 80 percent of a typical software project’s budget goes into
fixing defects that were created earlier on the same project.[2]
Figure 2-4 illustrates the way that
productivity erodes over time on a code-and-fix project. Little
or no effort is put into planning and process management at the
beginning of the project. Some small amount of effort goes into
thrashing (unproductive work), but most work goes into coding.
As the project moves forward, fixing defects becomes an
increasingly prominent feature of the project. By the end of the
project, the project that uses code-and-fix development is
typically spending most of its time fixing the defects that it
created earlier.
Figure 2-4
Using a code-and-fix approach, the lucky
projects finish while they are still eking out a small amount of
productive work. The unlucky projects get stuck in a zone where
100 percent of their effort is consumed by thrashing, planning,
and process management. (Source: Adapted from
Software Project Survival Guide.[3])
As Figure 2-4 suggests, the lucky
code-and-fix projects are brought to completion while they are
still eking out some small amount of coding progress. The
unlucky projects get stuck on the far right side of the diagram
where 100 percent of their available effort is consumed by
planning, process management, and thrashing, and they are not
making any coding progress. Without enough up-front planning,
the code quickly becomes flaky and brittle. Some of these
projects might be rescued by taking steps to push the team back
to the left enough that they can eke out a release. The
remaining projects are eventually cancelled.
This gloomy picture is no exaggeration.
Several studies have reported that about 25 percent of all
software projects are eventually cancelled.[4]
At the time the average project is cancelled, it’s 100 percent
over budget and is caught in an extended debug, test, and fix
cycle (thrashing). The reason it’s cancelled is the perception
that its quality problems are insurmountable.[5]
The irony of this dynamic is that these
unsuccessful projects eventually do as much planning and process
management as a successful project would. They have to implement
defect tracking to manage all the bugs being reported. They
begin estimating more carefully as the release date approaches.
Toward the end of the project, the project team might
re-estimate as often as every week or even every day. They spend
time managing expectations of project stakeholders, convincing
them that the project will eventually be released. They may
begin tracking defects and imposing standards for debugging code
before it’s integrated with already-debugged code. But because
they begin these practices late in the project, the benefits
from these practices are leveraged over only a small part of the
project.
The kinds of practices they implement are
different from the kinds a more effective organization would
implement in a project’s early stages. And many of the practices
they implement wouldn’t have been needed if the project had been
run well from the beginning.
As Figure 2-5 illustrates, the most
sophisticated organizations—those that produce the most reliable
software for the least cost and with the shortest
schedules—spend a relatively small percentage of their budgets
on the coding part of a project. The least sophisticated
organizations spend practically their whole budgets on coding
and fixing bugs in their code. Their total budgets are much
higher because they don’t lay any groundwork for working
efficiently. (I’ll return to this dynamic in more detail in
Chapter 9.)
Figure 2-5
Advanced software development approaches
require more work during the early stages of the project to
eliminate an enormous amount of unnecessary work in the later
stages of a project.[6]
Code-and-fix development continues to be
used because it is appealing in two ways. First, it allows the
project team to show signs of progress immediately—they can
begin moving the stone block 10 meters per day the first day,
while the more effective team is still out cutting down trees,
preparing the roadway for a smooth trip, and showing no visible
signs of progress on the real problem of moving the block. If
managers and customers aren’t very sophisticated about the
dynamics of a successful project, a code-and-fix approach looks
appealing. A second source of code-and-fix development’s appeal
is that it requires no training. In an industry in which the
average level of software engineering training is low, it has
been the most common method by default.
The code-and-fix approach is one form of
software fool’s gold. It seems attractive at first glance, but
experienced software developers recognize it as having little
value.
Focus on Quality
You might assume that a software project
can be shortened by spending less time on testing or technical
reviews. “Needless overhead!” say people with a taste for
code-and-fix development. Industry experience indicates
otherwise. An attempt to trade quality for cost or schedule
actually results in increased cost and a longer schedule.
As Figure 2-6 illustrates, projects that
remove about 95 percent of their defects prior to release are
the most productive; they spend the least time fixing their own
defects. Beyond about 95 percent defect removal, projects have
to expend extra effort to improve quality. Short of 95 percent,
projects can become more efficient by removing more defects
sooner. Approximately 75 percent of software projects presently
fit into this category. For the projects in this category, the
attempt to trade quality for cost or schedule is another example
of fool’s gold. It’s also an example of a software project
dynamic that isn’t really new. IBM discovered 25
years
ago
that projects that focused their efforts on attaining the
shortest schedules had high frequencies of cost and schedule
overruns. Projects that focused on achieving low defect counts
had the best schedules and the highest productivities.[7]
Figure 2-6
Up to a point, the projects that achieve
the lowest defect rates also achieve the shortest schedules.
Most projects can shorten their schedules by focusing on fixing
defects earlier. (Source: Adapted from
Applied Software Measurement:
Assuring Productivity and Quality, 2d Ed.[8])
Some Fool’s Gold Is Silver
Technologies and methodologies that are
associated with extravagant productivity claims are called
“silver bullets” because they are supposed to slay the werewolf
of low productivity.[9]
For decades, the software industry has been plagued by claims
that the UmptyFratz Innovation
dramatically improves development speed. In the 1960s, on-line
programming was associated with this claim. In the 1970s, it was
third-generation languages. In the 1980s, advocates for
artificial intelligence and CASE
tools
made
these promises. In the 1990s, object-oriented programming was
lauded as the next great productivity boon. In the early 2000s,
it was development in Internet time.
Suppose that a stone-block project team
starts out using the brute-force method to move the stone block.
After a few days, the team leader can see that progress isn’t
fast enough to meet the project’s goals. Fortunately, he has
heard of an amazing animal called an “elephant.” Elephants can
weigh almost 100 times
as much as an adult human being and are extremely powerful. The
project leader mounts an expedition to capture and bring back an
elephant to help the team move the block. After a three-week
safari, the team returns with a captive elephant. They harness
the magnificent beast to the block and crack the whip. They hold
their collective breath, waiting to see just how fast the
elephant will move the block. They may even finish ahead of
schedule! As they watch, the elephant begins pulling the block
forward, much faster than the team of humans had ever been able
to accomplish. But then, unexpectedly, the elephant rears on its
hind legs. It breaks its harness, tramples 2 of its handlers,
and runs off at 40 kilometers per hour, never to be seen again
(as shown in Figure 2-7). The stone-block team is dejected.
“Maybe we should have spent more time learning how to handle the
elephant before we started using him on a real project,” they
thought. They wasted more than 20 percent of their schedule
looking for the elephant, lost 2 of their teammates, and are no
closer to the goal than when they started.
That, in a nutshell, is Silver Bullet
Syndrome.
Figure 2-7
Silver bullet innovations often fall short
of expectations.
The elephant analogy is more apt than you
might think. Robert L. Glass chronicles 16 troubled projects in
Software Runaways.[10]
Four of the projects he describes expected to be breakthrough
successes because of their use of silver bullet innovations.
Instead, they ended up failing because of the same innovations.
A special kind of silver bullet is forged
from attempts to implement organizational process improvement
half-heartedly. Some organizations try to implement
organizational improvement with buzzwords—TQM, QFD, SW-CMM, Zero
Defects, Six Sigma, Continuous Improvement, Statistical Process
Control—these are all valuable practices when properly applied
by focusing on the substance of the practice and not just the
form. But each of these practices is virtually worthless when
applied as buzzwords. Some organizations cycle through them in
12-month intervals, as if ritualistically chanting the initials
of a current management fad could call forth improvements in
quality and productivity. A special place in low-productivity
hell is reserved for these organizations. After years of
Management By Buzzword (MBB), entire staffs become cynical about
organizational improvement initiatives in general, which adds
one more challenge to escaping from code-and-fix development.
The right innovation applied to the right
project, supported by appropriate training and deployed with
realistic expectations can be tremendously beneficial as a
long-term strategy. But new innovations aren’t magic and they
aren’t easy. When they are adopted with a get-rich-quick
attitude, innovations become fool’s gold.
Software Isn’t Soft
One more kind of fool’s gold is the belief
that software is soft. Hardware is “hard” because it is
difficult to change. Software was originally called “soft”
because it was easy to change. For very small programs at the
dawn of computer programming, this might have been true. As
software systems have become more complex, however, this notion
that software is easy to change has become one of the most
pernicious ideas in software development.
Several studies have found that changing
requirements—attempts to take advantage of software’s supposed
softness—are the most common or one of the most common sources
of cost and schedule overruns.[11]
They are also a major factor in project cancellations; in some
cases, changes resulting from creeping requirements can
destabilize a product to such a degree that it can’t be finished
at all.[12]
A simple example illustrates why software
isn’t as soft as people think. Suppose that you are asked to
design a system that will initially print a set of 5 reports and
eventually print a set of 10 reports. You have several kinds of
flexibility—softness—that you will need to be concerned about:
·
Is 10 an upper limit on the number of reports?
·
Will the future reports be similar to the initial
5 reports?
·
Will all of the reports always be printed?
·
Will they always be printed in the same order?
·
To what extent will the user be able to customize
the reports?
·
Will users be allowed to define their own reports?
·
Will the reports be customizable and definable on
the fly?
·
Will the reports be translated to other languages?
No matter how carefully the software is
designed, there will always be a point at which the software
won’t be soft. In the case of the reports, any of the following
areas could turn out to be “hard”:
·
Defining more than 10 reports
·
Defining a new report that is different from the
initial set of reports
·
Printing a subset of the reports
·
Printing the reports in a user-defined order
·
Allowing the user to customize reports
·
Allowing the user to define an entire custom
report
·
Translating the reports to another language that
uses a Latin alphabet
·
Translating the reports to another language that
uses a non-Latin alphabet or that reads right to left
What’s interesting about this example is
that I can ask a whole hat full of questions about the
“softness” of these reports without knowing anything whatsoever
about the specific reports or even about the system within which
the reports will be printed. Simply knowing that there are “some
reports” raises many general questions about the different
degrees of softness.
It’s tempting to say that software
developers should always design the software to be as flexible
as possible, but flexibility is an almost infinitely variable
entity, and it comes at a price. If the user really wants a
standard set of five pre-formatted reports, always printed as a
set, and always printed in the same order in the same language,
the software developer should not create an elaborate utility
that allows the user to generate highly customized reports. That
could easily cost the customer 100 to 1000 times as much as
providing the basic functionality the user really needs. The
user (or client or manager) has a responsibility to help
software developers define the specific flexibility needed.
Flexibility costs money now. Limiting
flexibility saves money now, but typically costs
disproportionately more money later. The difficult engineering
judgment is weighing the known present need against the possible
future need and determining how “soft” or “hard” to make the
“ware.”
How Fool’s Gold Pans Out
In conclusion, we hold the following
software truths to be self-evident (or evident after careful
examination, anyway):
·
The success of a software project depends on not
writing source code too early in the project.
·
You can’t trade defect count for cost or schedule
unless you’re working on life-critical systems. Focus on defect
count; cost and schedule will follow.
·
Silver bullets are hazardous to a project’s
health, though software industry history suggests that vendors
will continue to claim otherwise.
·
Half-hearted process improvement is an especially
damaging kind of silver bullet because it undermines future
improvement attempts.
·
Despite its name, software isn’t soft, unless it’s
made that way in the first place, and making it soft is
expensive.
The software world has had 50 years to
learn these lessons. The most successful people and
organizations have taken them to heart. Learning to resist
software’s fool’s gold consistently is one of the first steps
the software industry needs to take on the road to creating a
true profession of software engineering.
[1] This average is based on the
number of software projects at SW-CMM Level 1. See
Chapter 9 for more details about this statistic.
[2] Software Engineering Institute,
quoted in Fishman, Charles, “They Write the Right
Stuff,” Fast Company, December 1996. Mills,
Harlan D., Software Productivity, Boston, MA:
Little, Brown, 1983, pp. 71–81. Wheeler, David, Bill
Brykczynski, and Reginald Meeson, Software
Inspection: An Industry Best Practice, Los Alamitos,
CA: IEEE Computer Society Press, 1996. Jones, Capers,
Programming Productivity, New York: McGraw-Hill,
1986. Boehm, Barry W., “Improving Software
Productivity,” IEEE Computer, September 1987, pp.
43–57.
[3] McConnell, Steve, Software
Project Survival Guide, Redmond, WA: Microsoft
Press, 1997. This book contains a more in-depth
description of these dynamics.
[4] Johnson, Jim, “Turning Chaos into
Success,” Software Magazine, December 1999, pp.
30–39. The Standish Group, “Charting the Seas of
Information Technology,” Dennis, MA: The Standish Group,
1994. Jones, Capers, Assessment and Control of
Software Risks, Englewood Cliffs, NJ: Yourdon Press,
1994.
[5]Jones, Capers, Assessment and
Control of Software Risks, Englewood Cliffs, NJ:
Yourdon Press, 1994.
[6] The “advanced project” profile is
based on projects performed by NASA’s Software
Engineering Lab. The “typical project” is from project
data I’ve compiled from my consulting work and is
consistent with data reported by Capers Jones,
Patterns of Software Systems Failure and Success,
Boston, MA: International Thomson Computer Press, 1996,
and other sources.
[7] Jones, Capers, Programming
Productivity. New York: McGraw-Hill, 1986.
[8] Jones, Capers, Applied Software
Measurement: Assuring Productivity and Quality, 2d
Ed. New York: McGraw-Hill, 1997.
[9] Brooks, Frederick P., Jr., “No
Silver Bullets—Essence and Accidents of Software
Engineering,” Computer, April 1987, pp. 10–19.
[10] Glass, Robert L., Software
Runaways, Englewood Cliffs, NJ: Prentice Hall, 1998.
[11] Vosburgh, J., B. Curtis, R.
Wolverton, B. Albert, H. Malec, S. Hoben, and Y. Liu,
“Productivity Factors and Programming Environments,”
Proceedings of the 7th International Conference on
Software Engineering, Los Alamitos, CA: IEEE
Computer Society, 1984, pp. 143–152. Lederer, Albert L.
and Jayesh Prasad, “Nine Management Guidelines for
Better Cost Estimating,” Communications of the ACM,
February 1992, pp. 51–59. The Standish Group, “Charting
the Seas of Information Technology,” Dennis, MA: The
Standish Group, 1994. Jones, Capers, Assessment and
Control of Software Risks, Englewood Cliffs, NJ:
Yourdon Press, 1994.
[12] Jones, Capers, 1994,
Assessment and Control of Software Risks, Englewood
Cliffs, NJ: Yourdon Press, 1994.